[Construction Case] Fukushima Prefecture, Soma Port Port Maintenance Management Work (Quay Restoration)
Due to ground subsidence at the harbor's quay, there are steps and depressions in the concrete pavement, resulting in the loss of water gradient and the formation of puddles. This issue is resolved using the Upcon method.
The Upcon method, which allows for modifications without breaking existing concrete pavement slabs and within a short construction period, has been widely adopted in public works such as roads and airports as a maintenance and repair method. This time, we will introduce a construction site for correcting the sinking of concrete pavement slabs and filling voids at a quay in a port. The quay at Soma Port in Fukushima Prefecture, where cargo loading and unloading occurs frequently, has experienced issues due to ground subsidence, resulting in steps and sinking in the concrete pavement slabs, eliminating the water slope and causing puddles. This has hindered cargo operations. The Upcon method was chosen because it has no environmental impact compared to other methods and can correct the existing slabs without removal in a short period. [Site Information] Soma Port Port Maintenance Management Work (Quay Restoration) Construction Area: Approximately 285 square meters Maximum Subsidence: 97mm Construction Period: 4 days For detailed information on the construction process, please refer to the PDF download below.
Inquire About This Product
basic information
■ What is the Upcon Method? The Upcon method involves drilling small holes with a diameter of 16mm into concrete pavement slabs that have experienced sinking, unevenness, tilting, or gaps. While continuously monitoring the level in millimeter increments, polyurethane resin is injected. The resin injected beneath the slab immediately expands due to a chemical reaction, compacting and strengthening the ground, which improves the bearing capacity and lifts the concrete slab back into position using the pressure from the expansion. The required strength is achieved in about 120 minutes, significantly contributing to a shorter construction period. Additionally, if there are gaps beneath the concrete pavement slabs, the material can flow into small spaces and expand, allowing for complete filling without any voids. ■ Features of the Upcon Method 1. Short construction period: The construction time is 1/10 of conventional methods. 2. No need to stop operations: Heavy equipment or material relocation is unnecessary. 3. Comprehensive high technical capability: 100% in-house staff. 4. Compact construction system: Quick restoration of the current state is possible. 5. Reduced risk of re-sinking compared to conventional methods. We provide total support from on-site surveys to repair planning and construction, all handled responsibly by our in-house staff. Our specialized and experienced staff, trained in the field, will propose the optimal repair plan tailored to your site.
Price range
Delivery Time
Applications/Examples of results
Concrete pavement slab settlement correction work
catalog(5)
Download All Catalogs![[Construction Case Study / Port Edition Vol. 3] Repair Work for Port Facilities: Correction of Subsidence on RTG Travel Path](https://image.www.ipros.com/public/catalog/image/01/359/723873/IPROS56912473679892218552.jpeg?w=120&h=170)
![[Construction Case Study/Port Edition Vol. 1] Port Maintenance Management Work (Quay Restoration) Subsidence Correction and Void Filling](https://image.www.ipros.com/public/catalog/image/01/93a/646469/IPROS7250851689726681210.jpeg?w=120&h=170)
![[Construction Case Study / Port Edition Vol. 2] Onagawa Fishing Port Miyagazaki Quay Disaster Recovery Project](https://image.www.ipros.com/public/catalog/image/01/f20/647656/IPROS5098479422774090087.jpg?w=120&h=170)
Company information
We carry out construction to correct the sinking, tilting, steps, and gaps in concrete floors caused by uneven ground subsidence in buildings such as factories, warehouses, stores, and general residences, using our unique "Upcon Method" with completely non-fluorinated urethane resin and small machinery. Additionally, we are engaged in public works that utilize technologies developed through various research and development projects to restore the functionality of aging social infrastructure such as roads, airports, ports, and agricultural waterways. ■ Features of the Upcon Method 1. Short construction period: The construction time is 1/10 of conventional methods. 2. No interruption of operations: No need to move machinery or cargo. 3. Comprehensive high technical capability: 100% in-house employees. 4. Compact construction system: Quick restoration to the current state is possible. 5. Reduced risk of re-subsidence: Lower risk of re-subsidence compared to conventional methods. Our in-house staff provides total support from on-site surveys across the country to repair planning and construction, taking full responsibility. Our specialized and experienced in-house staff will propose the optimal repair plan tailored to your site. Upcon Co., Ltd. was newly listed on the Nagoya Stock Exchange Next Market on December 26, 2022.