Working scaffolding / Large wall formwork 'CB Climbing Bracket System'
PERI Climbing Formwork CB (Climbing Bracket)
Integration of climbing work scaffolding and the large wall formwork system VARIO for construction!
The "CB Climbing Bracket System" is a climbing system that integrates a working scaffold with the large wall formwork system VARIO. 【Product Features】 ■ It integrates the working scaffold and large wall formwork, allowing for climbing with a crane. ■ It is ideal for construction of high continuous sections, such as LNG storage tanks. ■ It reduces the labor of assembling and dismantling scaffolding, leading to labor savings and shortened construction periods. ■ By placing the formwork on a carriage that can move back and forth on the stage, it enables safe and efficient construction and stripping operations for each concrete pouring batch. *For more details, please refer to the PDF document or feel free to contact us.
Inquire About This Product
Related Videos
basic information
【Product Benefits】 ■ Improved formwork work efficiency ■ Significant reduction in workforce ■ Ensured accuracy in formwork construction ■ Reduction of scaffolding materials *For more details, please refer to the PDF document or feel free to contact us.
Price range
Delivery Time
Applications/Examples of results
At Perry Japan, we hold events at the Ibaraki Stockyard based on the concept of "Listen, See, Touch/Ride, Assemble" to learn according to our customers' needs. We conduct product exhibition tours of system formwork, study sessions on system formwork, assembly experiences, and product seminars. *For more details, please refer to the PDF materials or feel free to contact us.
Detailed information
-

Project Name: Ishikari LNG Base No. 4 LNG Storage Tank Expansion Work, specifically the expansion work of Ishikari LNG No. 4 Tank (Civil Engineering) Capacity: LNG Storage Volume 230,000 Kl (one of the largest in Japan) Construction Period: March 24, 2016 – October 30, 2020
-

One of the unique characteristics of this site is the harsh weather conditions. In addition to the winter shutdown period, there are days when winds comparable to typhoons blow, leading to downtime, which needed to be anticipated in the schedule. In such circumstances, there was a necessity for construction methods that could shorten the construction period.
-

(Customer Feedback) The construction workers had little experience with system formwork, but since special tasks were not required for the assembly, and it was basically repetitive work, we were able to start the work without any particular issues by having the sales representatives and construction instructors from PERI provide training in advance. While the systematized product allowed for increased efficiency, there were also challenges related to the inherent weaknesses of system formwork, specifically its lack of flexibility. For example, since the pitch of the tie rods is fixed, there are indeed parts where it is not as easy to avoid obstructions as it is with traditional methods. In such cases, we were able to find solutions by consulting with the technical staff and construction instructors from PERI and modifying the components as needed.
catalog(3)
Download All CatalogsNews about this product(6)
Company information
Perry Japan Co., Ltd. was established in January 2006 as one of PERI's bases in over 60 countries worldwide. Our staff, including sales, technical, and construction instructors, are dedicated to providing various PERI products and services to our customers in Japan. We are actively working to address the numerous challenges our customers face, such as improving safety and quality during concrete placement at construction sites, reducing labor, shortening construction periods, and cutting costs, by providing systematic formwork and shoring solutions. *Please feel free to contact us regarding the applications, technical materials, construction methods, techniques, and examples of PERI products.