[Construction Example] Large Product Storage Warehouse: Floor Slab Settlement Correction Work / Construction in 2010
Adopting the up-con method for short-term intensive repairs! Construction carried out with compatibility for multiple plant vehicles.
We would like to introduce a case of "floor sinking correction work" conducted at a large product storage warehouse in Ibaraki Prefecture. Due to the effects of ground subsidence, the stacked cardboard boxes were leaning. For concentrated repairs over a short period, the Upcon method was adopted, and our company carried out the work with multiple plant vehicles. 【Case Overview】 ■ Construction Area: Approximately 2,000m2 ■ Maximum Subsidence: 110mm ■ Location: Large product storage warehouse in Ibaraki Prefecture ■ Construction Period: 6 days (Day 1: 4 vehicles, Days 2-6: 2 vehicles for construction) *For more details, please refer to the PDF document or feel free to contact us.