Ground improvement / Lateral injection of ultra-high pressure hardening material for ground cutting 'JSG Method'
A method for creating cylindrical improved bodies up to 2 meters in height using cement-based hard materials on relatively loose ground. The work equipment is compact.
The JSG method involves cutting the ground by injecting a super high-pressure curing material liquid, accompanied by air, laterally from a rotating double-tube rod, while simultaneously discharging slime to the surface and creating a cylindrical improved body. 【Applications】 ● Improvement of the base during excavation / Pre-embedded underground beams ● Prevention of subsidence for newly constructed roads ● Shield launch and arrival protection ● Reinforcement of tunnels ● Strengthening of water-stopping in missing sections of earth retention work
Inquire About This Product
basic information
【Features】 Suitable for construction depths of up to 25m and relatively loose ground. A maximum improvement diameter of 2.0m can be expected with a small drilling diameter. Excellent adhesion to retaining walls and structures. The work equipment is compact and has excellent workability. Durability is outstanding due to the use of cement-based hardening materials. 【Construction Procedure】 1. Installation Install the JSG machine at the designated construction location. 2. Drilling Drill to the planned depth with rod rotation and stroke speed according to geological conditions. 3. Injection Test After drilling, set the steel pole insertion, rotation speed, and lifting time, and conduct an injection test. 4. JSG Construction Create piles by adhering to the specified lifting time and nozzle rotation. 5. Rod Withdrawal and Cleaning After completion of pile creation, withdraw the double-tube rod to the ground and clean the inside of the tube with clean water.
Price range
Delivery Time
Applications/Examples of results
【Applications】 ● Improvement of the base during excavation / Pre-embedded underground beams ● Prevention of subsidence for newly constructed roads ● Protection during shield launch and arrival ● Reinforcement of tunnels ● Strengthening of water-stopping in gaps of retaining walls
Company information
Since its establishment, our company has played a role in national construction, primarily focusing on the "ground improvement field" with our unique grouting method. Subsequently, in response to the changes in social infrastructure development, we have refined our technologies to adapt to the needs of the times and, at times, acquired new ones to expand our business scope. As a result, we have now established three main pillars: "ground improvement business," "slope disaster prevention business," and "pipeline business."