[Construction Case] Parts Assembly Factory: Floor Slab Settlement Correction Work
Due to the sinking of the floor, work was hindered! Here is an example of a case where corrections were made in a short period without stopping operations.
Here is an example of "floor sinking correction work" carried out at a parts assembly factory in Fukuoka Prefecture. Due to the sinking, the floor was slanted, making it difficult to adjust the jacks during conveyor assembly. As a result of the construction, we were able to improve the situation to the point where assembly work could be carried out smoothly. 【Case Overview】 ■Issue - The floor was slanted due to sinking, making jack adjustments during conveyor assembly cumbersome. ■Result - The situation was improved to the point where assembly work could be carried out smoothly. *For more details, please refer to the PDF document or feel free to contact us.
Inquire About This Product
basic information
【Construction Procedure】 1. Pre-construction measurement 2. Drilling for polyurethane injection work 3. Injection (1) 4. Polyurethane injection 5. Filling the hole *For more details, please refer to the PDF document or feel free to contact us.
Price range
Delivery Time
Applications/Examples of results
For more details, please refer to the PDF document or feel free to contact us.
catalog(7)
Download All Catalogs![Concrete pavement slab settlement correction method [Joint step difference and base slab settlement correction method]](https://image.www.ipros.com/public/catalog/image/01/2a4/608051/IPROS7464396502897123536.png?w=120&h=170)
Company information
We carry out construction to correct the sinking, tilting, steps, and gaps in concrete floors caused by uneven ground subsidence in buildings such as factories, warehouses, stores, and general residences, using our unique "Upcon Method" with completely non-fluorinated urethane resin and small machinery. Additionally, we are engaged in public works that utilize technologies developed through various research and development projects to restore the functionality of aging social infrastructure such as roads, airports, ports, and agricultural waterways. ■ Features of the Upcon Method 1. Short construction period: The construction time is 1/10 of conventional methods. 2. No interruption of operations: No need to move machinery or cargo. 3. Comprehensive high technical capability: 100% in-house employees. 4. Compact construction system: Quick restoration to the current state is possible. 5. Reduced risk of re-subsidence: Lower risk of re-subsidence compared to conventional methods. Our in-house staff provides total support from on-site surveys across the country to repair planning and construction, taking full responsibility. Our specialized and experienced in-house staff will propose the optimal repair plan tailored to your site. Upcon Co., Ltd. was newly listed on the Nagoya Stock Exchange Next Market on December 26, 2022.