[New Construction Case] We have uploaded the drainage pump station construction project.

We have uploaded a new construction case using the MT series high water content soil improvement agent, which addresses the high water content soil generated from the middle pile construction method. Please take a look at the link below.
Project Name: Drainage Pump Station Construction (Tentative Name)
Client: Niigata Prefecture
Construction Location: Niigata Prefecture
Project Overview: This project involves the construction of a drainage pump station. High water content soil is generated during pile driving using the middle pile construction method, so we were considering a simple treatment method. Additionally, consideration for the surrounding environment was an important issue at this site. Therefore, the neutral and dust-proof treated high water content soil improvement agent MT-2 was adopted, and after improving the soil with this product, it was immediately transported to a temporary storage site by dump truck.
Original Soil Water Content Ratio: Approximately 50%
Additive Amount: 3 kg/m3
Improvement Cost: 2,400 yen/m3
Improvement Time: Approximately 10 minutes
Recently, the adoption of this product in pile-related construction has significantly increased. If you are facing issues with soil treatment generated from similar projects, please feel free to reach out to us.