For the foundation of air conditioning outdoor units, eco-cute heat pump units, and oil tanks, as well as for various piping supports. For securing vending machines.
Possible to carry out construction without moving! Introducing a case where a settlement of up to 107mm was quickly corrected.
A housing foundation reinforcement method to prevent differential settlement of residential buildings! No contamination of the housing foundation or groundwater occurs!
A case study of correcting liquefied ground due to the earthquake! Maximum settlement of about 60mm was corrected in a day and a half.
Significant reduction in construction period and specialized in seismic performance!!
Low-cost earthquake measures! With two sliding sheets, the building's shaking can be reduced to a maximum of seismic intensity 5.
Can be installed on the wife's side and the waterside, and can be applied around the entire roof.
This is a catalog featuring components used for monolithic pouring, such as for slab foundations and mat foundations.
【Stain and White Bloom Prevention】Beautifully protect the appearance of the base and reduce complaints! Easy installation with just a peel-and-stick decorative elastic sheet. *One free F sheet for one building.
Corrected a maximum settlement of 46mm! A case that resolved the distortion of the door frame caused by settlement.
A maximum settlement of 500mm occurred! A case where the up-con method and single pipe pile driving method were used in combination for correction.
Maximum settlement of about 80mm due to earthquake and liquefaction! A case corrected in a short construction period of 2 days.
A maximum subsidence of 48mm occurred due to ground subsidence! Here we present a case of correcting subsidence within a short construction period of two days.
Even if the space between neighboring properties is very narrow, construction is possible! A maximum settlement of 66mm can be corrected in 3 days.
Systematization of housing evaluation operations! Clearly explaining the utilization image and benefits.
Marbles and golf balls rolling around... The cause of that floor, which should be level, may be due to changes in the ground. Before it worsens, start with a free consultation.
The cause of doors that won't close completely and gaps that won't fill may be the "tilt of the building"! We can solve your concerns by correcting the tilt through "settlement repair work"!
A fundamental review is necessary for "puddles" caused by earthquakes and ground changes! Subsidence correction work to repair building foundations and deformations *Free inspections available.
[Existing Construction Hardware] Measures against shaking from earthquakes, typhoons, etc.! Reinforcement of joints is possible.