[Case] Establishment of reference points due to the digitization of road ledgers.
Utilization of network-type RTK in the establishment of reference points due to the digitization of road ledgers!
We would like to introduce a case study utilizing network-based RTK in the "Establishment of Reference Points Accompanying the Digitization of Road Ledger" by Ariake Surveying Development Co., Ltd. 【Work Details】 ■ Installed 70 new points over a total length of 80 km * Network-based RTK involves observations of more than 10 epochs (single point observation method) 【Benefits and Effects】 ■ The conventional ground method using total stations took 30 person-days (3 people x 10 days), whereas this case was completed in 3 person-days (1 person x 3 days). ■ Significant cost reduction was achieved by reducing both work time and manpower. * For more details, please refer to the PDF document or feel free to contact us.
- Company:ジェノバ
- Price:Other